South Eastern Coalfields (SECL) is the second-largest coal producer among Coal India's subsidiaries, and its draft offer document has been on SEBI's filings list since 4 November 2026. Coal India, which owns all of it, plans to sell a tenth. This reads the draft for what the business is, how its numbers have moved, what it has paid its shareholder, and what it says can go wrong. The Coal India shareholder quota has its own piece.
How big it is. SECL mined 176.29 million tonnes in fiscal 2026, 16.94% of India's coal and 22.95% of Coal India's, from 55 producing mines in Chhattisgarh and Madhya Pradesh as of 31 March 2026. The Korba coalfield gave 133.40 million tonnes of that, about 75.67%. Its Gevra and Kusmunda opencast mines are ranked the world's second and fourth largest coal mines by capacity, according to the CRISIL report the draft quotes, and its audited reserves of 4.61 billion tonnes are, by the draft's reckoning, about 26 years at the fiscal 2026 rate.
Fiscal 2024: 187.38 million tonnes
Fiscal 2025: 167.49 million tonnes
Fiscal 2026: 176.29 million tonnes
Production fell, then recovered part of the way. It went from 187.38 million tonnes in fiscal 2024 to 167.49 in fiscal 2025 and 176.29 in fiscal 2026, and the draft lists the dip among its risks. In the six months to September 2026 it rose 5.81% to 76.88 million tonnes. The three mega mines, Gevra, Kusmunda and Dipka, hold environmental clearance for 172.50 million tonnes a year against 126 million tonnes produced in fiscal 2026, which the draft presents as room to grow.
The money, restated, Rs crore:
- Fiscal 2024: revenue from operations 32,783.62; EBITDA 10,670.75 (a 30.52% margin); profit after tax 6,930.77
- Fiscal 2025: revenue from operations 29,998.36; EBITDA 8,630.81 (26.16%); profit after tax 4,540.42
- Fiscal 2026: revenue from operations 32,956.52; EBITDA 9,364.87 (26.84%); profit after tax 4,754.59
- Six months to 30 September 2026: revenue from operations 16,593.78; EBITDA 4,029.36 (22.85%); profit after tax 2,174.35
So revenue in fiscal 2026 was back at fiscal 2024's level while profit after tax was not, and the EBITDA margin printed for the six months to September 2026 is the lowest of the four periods.
Cash and borrowing. Cash from operations was Rs 2,844.51 crore in fiscal 2024, Rs 4,506.28 crore in fiscal 2025 and Rs 8,979.94 crore in fiscal 2026. Capital spending on property and equipment was Rs 4,305.24 crore, Rs 3,999.10 crore and Rs 2,416.26 crore in the same years. Borrowings were Rs 4,985.45 crore at March 2024, Rs 7,137.80 crore at March 2026 and Rs 8,097.29 crore at September 2026.
What it pays its shareholder. As a state-owned company, SECL follows the government's rule for public sector enterprises: a yearly dividend of at least 30% of profit after tax or 4% of net worth, whichever is higher. The draft lists what it has declared, in Rs crore:
- Fiscal 2024: final 1,491.77, interim 599.91
- Fiscal 2025: final 794.99, interim 599.91
- Fiscal 2026: final 1,000.75, interim 774.94
- Six months to September 2026: interim 468.98, and 400.83 more from October 2026 to the date of the draft
The figures to set a price against. The draft prints earnings per share of Rs 7.19 for fiscal 2026, Rs 6.88 for fiscal 2025, Rs 10.43 for fiscal 2024 and Rs 3.30 for the six months to September 2026, all on the new Rs 2 shares, after a 1:1 bonus issue in February 2026 and a split in October 2026. Return on net worth was 25.70% in fiscal 2026, 29.07% in fiscal 2025 and 60.56% in fiscal 2024. The listed peers it names trade at 7.79 times earnings (Coal India), 7.97 (NMDC), 11.77 (PT Bukit Asam) and 20.45 (Yancoal Australia), an average of 12.00; it also lists Bharat Coking Coal, with no figure. A draft has no price band, so the IPO's own price-to-earnings is not known yet: once the band is out, the price divided by Rs 7.19 gives the figure to set beside these.
Who sells, and who gets the money. Coal India is selling up to 66,80,56,100 shares, a tenth of SECL's 6,68,05,61,000, and SECL issues no new ones, so the money goes to Coal India, not to SECL. The draft puts Coal India's weighted average cost at Rs 1.02 a share. Part of the offer is kept for Coal India's own shareholders.
What the draft says can go wrong, among its risks:
- Power-sector customers bought 65.34% of its coal in the six months to September 2026, and its top ten customers made up 50.31% of revenue from operations.
- Contingent liabilities were 72.08% of net worth on 30 September 2026.
- It is party to 387 tax cases, 230 direct and 157 indirect, with Rs 13,941.54 crore in dispute where quantified.
- It depends on Coal India, which controls it and whose interests may conflict with its own, and on Coal India's Central Mine Planning & Design Institute for exploration and mine planning.
- Leases with the Government of Chhattisgarh or Coal India, including for its registered office land, have expired and renewal is pending.
- A shortage of railway rakes, sidings or other transport could hold back how much coal it can move.
- Its previous auditors included emphasis of matters in their reports for fiscal 2024, 2025 and 2026.
Still to come: the price band, the offer price, the issue dates and the exact size of the shareholder quota, all in the red herring prospectus (RHP). A draft is not an approval. SEBI issues its observations first, terms can change, and some drafts never become IPOs.
Sources: South Eastern Coalfields Limited draft red herring prospectus, on SEBI's filings list from 4 November 2026 (our business, key performance indicators, basis for offer price, dividend policy, restated consolidated financial information, outstanding litigation, risk factors), and the CRISIL report it quotes. Information only. Not investment advice.